Final Spurt

After almost 8 months of construction, our building site is slowly but surely coming to an end. Since the last update, a lot has happened, especially in the outdoor area: our container could fly again and is now in its final location. In addition, the paving work has been completed and the steel construction is also almost finished. In any case, the bicycle parking lot was already inaugurated today! In addition, the exterior blinds have been installed. But there has also been a lot of work on the inside: the electrical system is almost completely in place, the paint is ready and we are now waiting for the screed to be ready for covering. The only major work still to be done is the flooring and the interior doors. That's a short to-do list! Thanks again to our neighbor Christian Tempel for the beautiful aerial photos! As always, the complete documentation of our extension can be read here.